CODES DU BÂTIMENT THERMODRAIN
Chez EcoInnovation Technologies, nous suivons et respectons les lignes directrices du code du bâtiment établies par chaque province.
Canadian Building & Plumbing Code Compliance Guide.
This statutory compliance brief provides building inspectors, municipal plan examiners, energy advisors (CEEs/CEAs), and mechanical engineers with the legal standards, code clauses, and local bylaws governing ThermoDrain® Drain-Water Heat Recovery (DWHR) installations across Canada.
City of Vancouver Building By-law (VBBL) & BC Energy Step Code
British Columbia and the City of Vancouver enforce distinct statutory requirements for DWHR that differ from standard model codes:
City of Vancouver By-law Rules
VBBL Book II & Part 10Under the consolidated Vancouver Building By-law (VBBL Book II - Plumbing Systems and Part 10 Energy Efficiency), two critical rules apply:
- Article 2.6.1.12.(2) (Plumbing System): "Drain water heat recovery units shall only be used to supply service water heaters." Preheating the cold feed directly to shower mixing valves (equal flow) is prohibited under the Vancouver Plumbing By-law.
- Sentence 10.2.2.11.(3) (Mandatory Multi-Family DWHR): In Part 10 buildings (excluding 1- and 2-family homes), DWHR is mandatory on the principal shower of each dwelling unit, requiring ≥ 42% steady-state efficiency under CSA B55.1 and CSA B55.2 double-wall construction.
- VBBL Energy Paths: Under Path 2 (Performance TEDI/MEUI), DWHR reduces domestic water heating electrical loads, keeping projects under the maximum operational GHG cap.
BC Energy & Zero Carbon Step Code
BCBC 9.36.6 / ZCSCWith Step 3 mandatory province-wide, leading BC municipalities (Richmond, City/District of North Vancouver, West Vancouver, Saanich, Kelowna) mandate Step 4 or Step 5 (Net-Zero Ready):
- MEUI Reduction: Installing a ThermoDrain (TDX3350 or TDX3615) provides an immediate 2.5 to 5.5 kWh/(m²·a) reduction in Mechanical Energy Use Intensity (MEUI).
- Envelope Trade-off Asset: Adding a DWHR unit avoids costly structural adjustments such as exterior continuous mineral wool (R-12 ci), triple-pane passive house window upgrades, or under-slab XPS foam.
- Zero Carbon Step Code (ZCSC EL-1 to EL-4): Shaves peak electrical demand during shower rush periods, preventing central or in-suite heat pump water heaters (HPWH) from triggering carbon-intensive electric resistance elements.
As provincial building codes accelerate residential fuel-switching toward Heat Pump Water Heaters (HPWHs), Canadian utilities (Hydro-Québec, BC Hydro, Ontario IESO) face extreme winter morning coincident peaks (6:00 AM–8:30 AM). In sub-zero Canadian design conditions, incoming municipal groundwater drops to 4°C–10°C (40°F–50°F). A single 9.5 L/min (2.5 gpm) shower demands over 17 kW of instantaneous thermal power, rapidly exhausting tank capacity and forcing dual 4,500W electric backup resistance elements to engage across thousands of homes simultaneously. Passive DWHR reduces instantaneous shower demand by 30% to 50%, pre-warming incoming water to ~25°C, preserving tank stratification, and preventing costly winter backup element snapback.
Preheat to Water Heater ONLY (Equal Flow Prohibited)
Under Chapter III (Plumbing) of the Quebec Construction Code and CMMTQ inspection standards, DWHR preheating must route exclusively to the cold water inlet of the water heater. Feeding tempered water into the cold port of a pressure-balanced or thermostatic shower valve compromises anti-scald protection and will fail provincial inspection.
Toronto Green Standard (TGS Version 4 - Tier 1–3)
TGS sets aggressive caps on Total Energy Use Intensity (TEUI) and Greenhouse Gas Intensity (GHGI) for multi-unit residential buildings (MURBs). ThermoDrain 4-inch cores (TD442, TD460, TD472) on centralized drainage stacks are a primary Domestic Water Heating Energy Conservation Measure (ECM) for Tier 2/3 development charge refund eligibility.
Cross-Canada Plumbing & Building Code Harmonization Matrix
Summary of code articles, minimum efficiency baselines, and piping rules by jurisdiction:
Technical Note: Homes with Septic Systems (OBOA Building Advisory)
In homes constructed with private on-site septic systems, the building drain often exits through the foundation wall 3 to 4 feet above the basement floor. This can restrict vertical clearance beneath first-floor shower traps:
- Early Plan Coordination: Plan the drain stack layout during initial framing to ensure the DWHR unit is positioned vertically above the building drain invert elevation.
- Walkout Basements: Walkout lots naturally drop the septic tank elevation, providing full vertical clearance.
- Compact Core Selection: The 24-inch ThermoDrain TDX3240B requires only 28 inches of vertical stack clearance, making it suitable for tight mechanical rooms or raised septic building drains.
Plumbing Inspector On-Site Verification Checklist
Field checklist for municipal inspectors conducting rough-in and pre-drywall inspections:
The heat exchanger must be mounted vertically on the drainage stack. The unit must be within 5 degrees of true vertical to guarantee falling-film annular surface adhesion across the entire copper inner circumference.
TDX Series: Direct solvent weld connections using standard approved ABS or PVC cement.
TD4 & TDH Series: Connected using heavy-duty, shielded stainless-steel mechanical couplings (e.g., Fernco Proflex). Non-shielded rubber slip-couplings are not permitted.
Cold municipal supply water must enter the bottom port and exit through the top port. This establishes the required counterflow dynamic against downward-flowing greywater.
Inspect the visible vented air gap collar to ensure it has not been caulked, taped, or spray-foamed shut. The atmospheric capillary relief gap (CSA B55.2) must remain open to ambient air.
HOT2000 & Building Simulation Input Parameters
Energy Advisors (CEEs/CEAs) evaluating homes or buildings for EnerGuide, Novoclimat, Net Zero, or BC Step Code ratings must model the system using the following exact steps:
- Navigate to the Domestic Water Heating (DHW) component screen in HOT2000 (v11 or v12).
- Enable the Drain-Water Heat Recovery (DWHR) module checkbox.
- Select configuration: "Preheating to Water Heater Only" (Mandatory in QC and City of Vancouver; standard in other jurisdictions unless dual-feed is verified on-site).
- Select shower drain configuration: Specify the percentage of total home showers that drain through the unit (typically 100% when all upper/main showers route to the 3" core).
- Input the certified CSA B55.1 efficiency rating directly from the NRCan Searchable Product List:
- TDX3240B (24" core): 33.59%
- TDX3350 (35" core - Meets OBC SB-12 & VBBL 42%): 42.10%
- TDX3615 (61.5" core - High Performance / Net Zero): 55.04%
- TD442 (4" × 42" commercial stack): 46.20%
- TD460 (4" × 60" commercial stack): 55.30%
- TD472 (4" × 72" commercial stack): 59.10%